Stay informed on the the progress as milestones are reached by checking back here.
Thank you to the volunteers working hard to get this project done as quickly and as cost effective as possible. The donation of time, material, and equipment has helped defray costs to make this project a reality!
The State of New Hampshire has mandated that our pumphouse is brought up to current standards due to the numerous issues and violations. The system was installed decades ago and is well past it's useful life. Confined space regulation and pressure tank failure are the official state violations which we must demonstrate are being resolved. In addition, the aging system could fail resulting in a no water situation which is why we must act quickly to replace.
Below is a gallery tour of the current pump house and equipment we are relying on to provide water. The photos outline the poor condition and issues visually. Here are some of the deficiencies and concerns that the project will address:
Construct a pump house addition to contain all new infrastructure while allowing the existing system to operate. Once complete, the old system will be shut off and seamlessly switched to the new one. The existing pump house will then be repurposed by filling in the basement and pouring a slab to house a large backup storage tank. This tank will provide extra water volume capacity for peak usage, growth, and provide temporary water in the event of well pump failure or servicing.
The project is divided into three phases across 2023 and 2024 to spread costs out and use annual assessments to fund. Current budget estimations should allow the project to be funded with the new annual assessment of $1200 collected from members for this year and the next year. This all hinges on water billing collections, member cooperation, volunteers, and no other water system failures requiring money along the way.
Phase I (Fall 2023 completion)
Phase II ( Spring 2024 completion)
Phase III (Fall 2024 completion)
All the required state and local permits have been received and approved for construction. Building permit is displayed on the existing pumphouse.
Silt fence installed and foundation dug ready for forms.
Forms set ready for concrete.
Forms stripped, backfilled, and rough graded.
Rebar for monolithic slab to support weight of tanks and equipment along with required floor drain plumbing.
Finished Floor
Pressure treated sill plate installed ready for framing.
Official Address 64 Rebecca Lane. New Secure Mailbox Installed.
Door Donation
Humidity Fan
Siding Donation
Metal Roof Installed
Weather tight addition
Epoxy Floor for easy cleaning and floor drain complete.
Insulation complete
Staging use donation
Zip system backer board ceiling complete
Air Circulation vents and wind dams installed
Zip system wall backer board complete
Primary Water Tank Delivery
Installation
Installed
New Modern Pumps. No pressure tanks needed.
Pump Controllers
Pump Controllers
Controls
Plumbing
Pump Controllers
Well Pump Control
New Panel and Generator Transfer Switch
Copyright © 2024 Rebecca Lane Water System Association - All Rights Reserved.
Powered by GoDaddy
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.